Main Avenue work progressing on schedule

Email News Alerts

Work is continuing at a steady pace on Main Avenue reconstruction, with October 17, targeted as the completion date for the first phase of the entire project which began in mid-May.

Focus during the month of September will be on installing the remainder of the pavement, curb and gutters and sidewalks and paving the frontage roads, followed by the remaining electrical work and landscaping in October.